A M Water Services Ltd — Integrated Management System

SOP 5.1 Production, Issue & Briefing of RAMS

Issue 3 | 1 May 2026
Document ReferenceSOP_5.1
Issue Number3
Issue Date01/05/2026
Next Review01/05/2027
Approved ByAaron Mason, Director
Controlled ByAaron / Leanne Mason · Sean Ashton

Production, Issue & Briefing of RAMS

ISO 9001:2015 Clause 8.5 · ISO 45001:2018 Clauses 6.1.2 & 8.1.2 — Operational planning and control; production of risk assessments and method statements

Procedure overview
A M Water Services produces task-specific Risk Assessments and Method Statements (RAMS) for every operational activity, building on the master risk assessments held in the Van Packs portal. The HSQE Consultant drafts each RAMS to current legislation, industry standards and best practice; the Directors review and approve before issue. Approved RAMS are delivered to the field team in hard copy or electronically, briefed face-to-face before work commences, and supplemented by a dynamic Point of Work Risk Assessment (PowRA) on first arrival at site. RAMS, briefing sheets and PowRAs are retained in the project file per SOP 4.7. The Van Packs portal serves as the operative-facing master copy of the standing risk assessments and method statements; client/project-specific RAMS produced under this SOP are bridged from those master documents.

Production, Issue & Briefing of RAMS — Process Flow

RAMS Producer
Sean Ashton (HSQE Consultant)
Draft
Draft Risk Assessments and Method Statements ensuring compliance with current legislation, industry standards and best practice
APP_07 OHS Hazard Assessment
Issue draft RAMS for review, comment and approval
Receive comments back; make changes and ensure all comments are incorporated from previous review cycles
RAMS Reviewer / Approver
Aaron Mason (MD)
Leanne Mason (Director)
Review & Approve
Review draft RAMS
RAMS approved?
No
Issue comments back to RAMS author for revision
Yes
Approve, sign and date RAMS confirming approved for issue
Issue approved RAMS to team(s) (hard copy or electronically via tablet)
Site Supervisor & Team Leader
Jason May (Supervisor)
Team Leaders · Operatives
Brief, PowRA & Retain
Receive approved RAMS (hard copy or via tablet)
Brief approved RAMS to all relevant site staff prior to work commencing; collect signatures on briefing sheet
Carry out dynamic Point of Work Risk Assessment (PowRA) on first arrival at site, before work starts
PowRA template
Retain approved RAMS, signed briefing sheets and PowRA in the project file (paper or electronic)
SOP 4.7 Control of Records
Process / Activity
Decision Point
Document / Cross-reference
Approve / Continue
Revise / On-site Reassessment
Point of Work Risk Assessment (PowRA) — mandatory before every site start
A pre-approved RAMS describes the planned conditions on site. The actual conditions on the day — weather, ground state, third-party works, traffic, presence of public, unexpected services, plant availability — will always differ. Every operative crew must complete a Point of Work Risk Assessment on first arrival at site, before any work commences, to verify the planned controls remain valid for the actual conditions. If the PowRA identifies any condition that materially changes the risk profile, work does not start until: (1) the issue is reported to the Site Supervisor; (2) revised controls are agreed; (3) the revised RAMS or supplementary briefing is delivered and acknowledged. PowRA records are retained alongside the master RAMS for the duration of the project plus 3 years per SOP 4.7.